In a recent arbitration, almost 12 years after
completion of a new-build, low-rise block containing flats, shops and
communal facilities, a developer claimed against his builder for
water damage. The developer particularised
the claim in terms of design defects with a few sweep-up allegations of poor
workmanship. The remedial scheme
commissioned by the developer involved a redesign of that part of the building
alleged to be at fault. The developer
sought compensation from the builder for the full cost of the remedial works.
The builder confidently rejected liability for
the cost of correcting design flaws as the design was produced by the
developer’s chosen architect whose design the builder had been obliged to accept.
While the builder correctly understood how the
design work had been undertaken, insufficient attention had been paid to the
peculiar split between design liability and design duty under the building
contract. The builder had entered a
modified JCT design and build contract.
This made the builder liable for negligent design while requiring the
builder: to engage the developer’s architect, to implement the architect’s
design and not to alter the architect’s design.
Thus the builder had liability
for a design over which he had no control.
The design, as evidenced by the drawings, was
completed more that 12 years before the action was brought. Practical completion was less than 12 years
before the action was commenced. The
developer held that, as a builder’s duty continued until practical completion,
the action was not statute barred. The
builder disagreed, holding that if the action was statute barred against the
architect, insofar as the claim was for deficiencies in the architect’s design,
it must also be statute barred against the builder. The developer also argued that there was an
implied continuing duty to review the design during inspections. However the building contract did not include
a requirement for, and the architect was not engaged to carry out, routine
periodic architectural inspections during the works.
From the outset, reports by the project
insurer’s surveyor, the occupant’s surveyor and the developer’s surveyor
informed the legal proceedings and formed the basis for the remedial work,
which was completed earlier this year. It was while the case was approaching a
hearing and after the remedial work was complete that I was invited to prepare
expert evidence and still later that the developer obtained an expert report.
I reported that the design was flawed (but not as the developer asserted) and that the
developer’s remedial scheme was similarly flawed. The developer’s expert advised revising the developer’s case and the builder, on
receipt of the developer’s expert’s report, stated that it raised issues other
than those pleaded and applied to have much of it struck out unless the claim
were revised. Such a late fundamental
revision to the Statement of Case may have exposed the developer to a claim for
abortive costs and the developer eschewed this advice and resisted the
application. The
arbitrator was minded to allow the claimant’s expert evidence on the basis he
could properly ignore any part of it which did not go to the pleaded issues.
Both parties, now close to a hearing, were in
possession of expert evidence which put into question the validity of the claim
as pleaded but which showed there was, subject to the Statute of Limitations, a
viable claim. The developer’s costs already
exceeded the sum claimed and the anticipated costs to go to a full hearing
would make the parties’ costs greatly exceed the sum in dispute. The result was a compromise settlement following the experts’ meeting.
Regrettably, due to the legal costs incurred, the settlement left both
parties out of pocket by more than the sum claimed. A high price to pay for the experienced
gained. An earlier reading of the
contract documents and appointment of experts could have brought the dispute to
a cheaper, quicker and more effective resolution.
No comments:
Post a Comment