An adjudicator telephoned an expert to ask about the correct
method of constructing a sand-and-cement floor screed. The case the adjudicator was considering
involved the incorrect placement of a reinforcing mesh in a screed.
The
expert described to him the alternatives which would have ensured correct construction. The expert gathered from his conversation
with the adjudicator that the mesh was generally laid below the screed but was
in some places poking out from it. No
other fault was reported.
Whilst
the expert confirmed that the mesh, to perform its intended purpose, should be
placed centrally in the screed, he also advised that the screed may work
adequately without reinforcement – that, in fact, the incorrect incorporation
of reinforcement may not cause widespread damage. The adjudicator had, however, already made up
his mind that the claim was justified on the basis that the construction was
faulty regardless of the consequences thereof.
In the above
floor-screed adjudication, the defendant might have successfully argued that
the fault in the placement of the screed had caused no more than minor damage
which could be corrected at a much lower cost than the complete replacement of
the screed. His argument that the work
was not defective was weak
but an argument that complete replacement of the screed was unnecessary would have had some force. Mitigation of loss should be taken into account.
but an argument that complete replacement of the screed was unnecessary would have had some force. Mitigation of loss should be taken into account.
No comments:
Post a Comment